Mozambique:
Power Efficiency and Reliability Improvement Project (PERIP): Consulting Services for Engineering Design and Construction Supervision for Emergency Rehabilitation & Reinforcement of Transmission and Distribution Networks Project, Phase I

Objective of the Power Efficiency and Reliability Improvement Project (PERIP) is to define, finance and implement emergency priority measures to alleviate the most critical supply constraints in EDM's transmission and distribution grid. Phase I encompasses design and preparation of tender documents.


Services
  • Design of substations and transmission lines
  • Update / preparation of system studies
  • Preparation of technical specifications
  • Specifications for risk mitigation plans, ESIAs, EMPs and RAPs
  • Definition of telecommunication and SCADA systems
  • Preparation of tender documents and cost estimates
  • Support during tendering and award for 5 lots
Technical Data
  • 66/11 kV and 110/33 kV 40 MVA power transformers
  • Substation improvements to double busbar systems
  • 66 kV overhead transmission lines and underground cables
  • 150 MVAr STATCOM
  • 220 kV shunt reactor
  • Replacement of control and protection
  • Rehabilitation and extension of distribution networks
  • 220 and 110 kV switchgear replacement and substation extensions

Client:
Electricidade de Moçambique E.P. (EDM)
Financing:
EDM
Period:
2017 - 2020