ADVISORY SERVICES FOR THE INTRODUCTION OF IT SYSTEMS
DESIGN AND IMPLEMENTATION OF ELECTRICAL NETWORKS AND SUBSTATIONS
- Development and derivation of possible emergency scenarios fortheelectrical operations management
- Development of an overarching emergency concept to maintain electrical operations management for a total of 9 nationwide regional control centers, taking into account site-specific requirements
- Creation of a valid emergency manual including site-specific annexe
- Development of a harmonizedprocessmodelforthe electricaloperationsmanagementfor a total of 9 nationwide regional controlcenters
- Development and differentiationofthesupportingprocessesintocentralized and decentralizedareasofresponsibility
- Transferring theprocessmodelintotheprocesslandscapeof DB Energie GmbH (SAP Signavio) and perform a detailed modeling oftheprocessesaccordingto BPMN 2.0
- Documentationofthe operational concept
- CONSULECTRA supportsthe sub-projects within theareaofprocessmanagementwith a focus on energyindustryrelatedtopics
- Support in thedevelopmentofoverarchingprocessmodelswithinthe sub-projects, takingintoaccounttherequirementsoftheregulatoryauthorities
- Modeling and technical release oftheprocessesidentified in the sub-projects accordingto BPMN 2.0
- A coherent interconnected control system is being implemented to integrate the network control tasks of a total of 9 nationwide regional control centres for the operation of the German Rail's electrical networks.
- The system was designed and put out to tender with the help of CONSULECTRA; it is currently in the implementation phase.
- CONSULECTRA has created a migration concept for the complex switchover and developed operating processes and an emergency concept.
- For the introduction of a network analysis platform, CONSULECTRA conducted an analysis of requirements and subsequently elaborated the specifications.
- The network analysis platform is intended to support the electricity supply system of German Rail by means of mass assessment and archiving of measurement data and fault reports.
- CONSULECTRA gave advice during the EU tender procedure and supports with the elaboration of the functional design specifications and the implementation of the platform.
DB Energie operates an own transmission- and distribution network at high-voltage level (110 kV, 16.7 Hz) for the nationwide distribution of electrical energy. The coordination and monitoring is ensured by the network-control-center "Hauptschaltleitung" (HSL). CONSULECTRA was commissioned to support the planning, procurement and implementation of the HSL and to ensure the functional future-proofing of the control system. The following project phases have been completed to date:
- Preliminary study (pre design planning) for the conceptual design of the renewal of the HSL (2022)
- Preparation of specifications (draft planning) for the renewal of the HSL (2022 - 2023)
- Supporting the tender and bid evaluation for the renewal of the HSL (since 2023)
Technical advice and support of the project management in the Redispatch 2.0 project
- Rough conception for the implementation of Redispatch 2.0
- Process analysis and determination of the affectedness
- IT target concept and determination of the need for action
- Development of an implementation concept as a basis for the following steps
- Support in the implementation of Redispatch 2.0 with regard to organisational measures, expansion, adaptation and introduction of IT systems and coordination with market partners
.
Technical consulting and support of the project management in the project Querverbundleitstelle 2.0
- Conceptual design and preparation of specifications for the renewal of the cross-connection control system within the scope of an upgrade
- Support with tender evaluation and awarding
- Accompaniment of the realisation in all project phases up to acceptance
.
- Review of the current redundancy concept – with regard to organisational and technical aspects – in the area of network control and determination of the need for action
- Conducting a risk analysis based on a structured as-is analysis and developing practical recommendations for action for the implementation of the previously developed redundancy concept for the control centre facilities of E.DIS Netz GmbH
- Analysis of the supporting processes for secondary technology (network control technology and telecontrol technology) and development of a process model
- Recording of the effort of the various tasks and activities of the process model
- Plausibility check of the recorded effort on the basis of benchmarks with comparable network operators
- Development of measures for reducing or shifting the workload
- Determination of the resulting personnel requirements for the defined task areas
- Development of job descriptions and qualification requirements for filling new positions
Technical advice in the Redispatch 2.0 project
- Rough conception for the implementation of Redispatch 2.0
- Process analysis and determination of the affectedness
- IT target concept and determination of the need for action
- Development of an implementation concept as a basis for the following steps
- Conducting a requirements analysis for the renewal of the cross-connection control system
- Preparation of a specification sheet for the preparation of the EU tendering procedure
- Accompaniment of the EU tender with decision recommendation for the award of contract
- Support in the preparation of specifications and realisation of the new cross-connection control system up to the acceptance date
- Project support for the procurement and introduction of a cross-network control system
- Elaboration of specifications
- Tendering and bid evaluation
- Project support with assistance in elaboration of functional specifications, functional testing (FAT, SAT) and acceptance
Support in the procurement of a fault management system to support the fault clearance processes with
- Requirement analysis and creation specifications
- Offer analysis for the procurement of a fault management system
- Project support for system introduction
- With the aim of replacing a large number of existing systems, we are supporting Stromnetz Berlin in the introduction of an Advanced Distribution Management System (ADMS) for the high-, medium- and low-voltage grid
- The ADMS was first designed and put out to tender together with Stromnetz Berlin, then the system analysis was supported
- CONSULECTRA is currently supporting the realisation phase of the ADMS and assisting in the management of the project programme "Betriebsführungskonzept - BFK Berlin".
- Project management and technical support in the Redispatch 2.0 project
- Concept development for mapping the redispatch processes in existing and new systems
- Evaluation of the offers obtained for the adaptation of existing software systems and for the creation of new software
- Support during implementation, including technical evaluation of the solution concepts and acceptance tests
- Concept study for the design of an assistance system in system management for the technical coordination of curative congestion management measures in real-time operation
- Development of different architecture concepts from fully integrated to modular with regard to functional areas such as SCADA, data management, process coupling, power-frequency controller, grid control network, online grid analysis, predictive grid analysis, dynamic grid security calculations
- Consideration of future developments and interfaces to other internal IT systems, to other European TSOs, to subordinate DNOs
- Evaluation of the concept approaches with regard to criteria such as maintainability, usability, hardware efficiency, functionality, reliability
IT sub-project management for the tender and introduction of a TSO platform for the Europe-wide optimisation of secondary control power deployment as part of the PICASSO project (Platform for the International Coordination of Automated Frequency Restoration and Stable System Operation)
- Requirements specification
- Bid evaluation
- Project support with assistance in drawing up specifications, functional tests (FAT, SAT) and acceptance
- Development of a concept for a platform for advanced network analysis to create greater vendor independence, increase flexibility for the development and introduction of new applications with minimal impact on ongoing operations of management processes
- Functional concept with analysis of the relevant processes and functions as well as evaluation of possible functional cuts for a modular structure
- Verification of the solution approach through a market survey
- System-technical concept with analysis of the basic system-technical boundary conditions and the required interfaces as well as the framework conditions for system operation
- Implementation concept for the development of the platform